Valley Lo Lane Improvements
2025 Capital Improvement Project
The proposed watermain project includes approximately 0.7 miles of improvements on Valley Lo Lane from Tanglewood Drive to Wildberry Drive broken down into two phases.
Phase I - Monroe Ave to Wildberry Drive. Completed in 2024.
Phase II -Monroe Ave to Tanglewood Drive. Construction scheduled for 2025.
The following major improvements are included in this project:
- Installation of approximately 1,600 feet (Phase I) and 1,400 feet (Phase II) of 8-inch Polyvinyl Chloride (PVC) water main with new 1.5-inch water service lines and b-boxes
- Pavement patching
- Parkway and driveway restoration for areas affected during construction
- Resurfacing all of Valley Lo Lane after water main is completed in 2025
Tentative Schedule
- Bid award date – January 7, 2025
- Starting date of construction – March 2025
- Approximate completion of construction – May 2025
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.
May 16, 2025 05/16/2025
The week of May 12 the contractor patched the roadway and finished restoring any landscaping that was damaged during construction.
Good News! The project is substantially completed, and this will be the final blog post for the Valley Lo Phase 2 Water Main installation Project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.
The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
May 9, 2025 05/09/2025
The week of May 5 the contractor repaired curb and gutter that was damaged due to construction.
The week of May 12 the contractor plans on patching the roadway where they installed the new water main and is tentatively planning on performing final landscaping.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
May 2, 2025 05/02/2025
The week of April 28 the contractor prepared the road for asphalt patching. They also prepped the curb and gutter for repair by removing any curb and gutter that was damaged during construction.
The week of May 5 the contractor is tentatively scheduled to pour back new curb and gutter. Also, the contractor is tentatively planning on patching the road late in the week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
April 25, 2025 04/25/2025
The week of April 21 the contractor finished all underground improvements. This includes the installation of the new water main and water services.
The week of April 28 the contractor is tentatively scheduled to begin repairing curb and gutter that was damaged during the project. This work is tentatively scheduled to last one week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
April 21, 2025 04/21/2025
The week of April 14 the contractor installed new water services. The new water services connect each house with a new 1.5” copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of April 21 the contractor will continue installing new water services starting where they left off the previous week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
April 11, 2025 04/11/2025
The week of April 7 the contractor installed new water services. The new water services connect each house with a new 1.5” copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of April 14 the contractor will continue installing new water services starting where they left off the previous week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
April 4, 2025 04/04/2025
The week of March 31, 2025 the contractor began installing new water services. The new water services connects each house with a new 1.5” copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of April 7, 2025 the contractor will continue installing new water services starting where they left off the previous week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
March 31, 2025 03/31/2025
The week of March 24, 2025 the contactor finished the installation of the water main. After installation was completed, the new water main underwent standardized testing needed before it can be put into service. These tests including pressure testing and water main chlorination. While these tests are taking place the contractor installed storm sewer repairs at certain locations throughout the project limits.
The week of March 31, 2025 the contractor will begin installing new water services. The new water services connects each house with a new 1.5” copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9 or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
March 21, 2025 03/21/2025
The week of March 17, 2025, the contractor continued installing water main starting where they left off the previous week.
The week of March 24, 2025 the contactor is tentatively planned to finish the installation of the water main. After installation is complete, the new water main is required to undergo standardized testing before it can be put into service. These tests including pressure testing and water main chlorination. While these tests are taking place the contractor plans on making storm sewer repairs at certain locations throughout the project limits.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9
or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
March 14, 2025 03/14/2025
The week of March 10, 2025, the contractor began installing new water main starting at the intersection of Tanglewood and Vally Lo and working east. Installation of the new water main is anticipated to take four weeks.
The week of March 17, 2025, the contractor will continue installing water main starting where they left off the previous week.
Please watch for further information via the project website at https://www.glenview.il.us/index.php?section=construction-projects&projectsection=2&project=9
or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
March 7. 2025 03/07/2025
Welcome to the project updates page for Valley Lo Phase 2 Water Main Installation Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Brothers Inc. of Elk Grove Village Illinois.
The week of March 10, 2025, the contractor will begin installing new water main tentatively beginning at the intersection of Tanglewood and Vally Lo and working east. Installation of the new water main is anticipated to take four weeks.
The week of March 17, 2025, the contractor will continue installing water main starting where they left off the previous week.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at
or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
May 24 Update 05/24/2024
The week of May 20, 2024, the contractor will finish installing water services. After all the water services are complete the contractor will begin phase II of construction, the restoration portion of the project. The contractor will begin restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
The week of May 28, 2024, the contractor will continue to restore the areas affected by construction where they left off the previous week. The contractor will continue restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website here or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
May 17 Update 05/17/2024
The week of May 13, 2024, the contractor will continue installing new water services starting where they left off the previous week.
The week of May 20, 2024, the contractor will finish installing water services. After all the water services are complete the contractor will begin phase II of construction, the restoration portion of the project. The contractor will begin restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
Please remember these dates are dependent on suitable weather.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Underground work 05/03/2024
The week of April 29th, the contractor also completed standardized testing including pressure testing and chlorinating the new water main in the south portion. The contractor will continue installing new water services to each home affected home. The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of May 6, 2024 the contractor will continue installing new water services starting where they left off the previous week.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Construction Water Main Installation 04/26/2024
The week of April 22 the contractor completed installing water main on the south portion of Valley Lo. The contractor also began standardized testing including pressure testing and chlorinating the new water main in the south portion. The contractor will continue installing new water services to each home in the north area. The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of April 29, 2024 the contractor will continue installing new water services starting where they left off the previous week.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24-25ValleyLo.aspx or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Underground work 04/19/2024
The week of April 15 the contractor continued installing water main working towards Wildberry. Throughout this phase of construction, the contractor will be working in the street. installation of the new water main is anticipated to last approximately two weeks.
The week of April 22 the contractor will continue installing water main on the south portion of Valley Lo. The contractor is tentatively scheduled to begin installing new water services to each home..
The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
YOUR EMAIL ADDRESS IS SUCCESSFULLY REMOVED FROM UPDATE ALERT LIST.
Capital Improvement Program

The Village annually updates its five-year Capital Improvement Program.
2025 Capital Improvement Program Map
2025-2029 Capital Improvement Program Map
2025-2029 Capital Improvement Program List
You can make suggestions and leave feedback about conditions of infrastructure for the next CIP by dropping a pin in this interactive map.
Valley Lo At-A-Glance
Contractor: DiMeo Brothers Inc.
Budget: Phase I: $924,000
Phase II: $800,000
Valley Lo Project Library
Tim Schwister
Project Manager
(847) 904-4422Jon Trent
Capital Projects Manager
(847) 904-4236What can we help you with today?
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.