May 24 Update 05/24/2024
The week of May 20, 2024, the contractor will finish installing water services. After all the water services are complete the contractor will begin phase II of construction, the restoration portion of the project. The contractor will begin restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
The week of May 28, 2024, the contractor will continue to restore the areas affected by construction where they left off the previous week. The contractor will continue restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website here or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
May 17 Update 05/17/2024
The week of May 13, 2024, the contractor will continue installing new water services starting where they left off the previous week.
The week of May 20, 2024, the contractor will finish installing water services. After all the water services are complete the contractor will begin phase II of construction, the restoration portion of the project. The contractor will begin restoring curbs, driveways and sod that was damaged during construction. Residents will be notified in advance of not having access to their driveways during the curb repair. This is anticipated to last approximately two weeks.
Please remember these dates are dependent on suitable weather.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Underground work 05/03/2024
The week of April 29th, the contractor also completed standardized testing including pressure testing and chlorinating the new water main in the south portion. The contractor will continue installing new water services to each home affected home. The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of May 6, 2024 the contractor will continue installing new water services starting where they left off the previous week.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Construction Water Main Installation 04/26/2024
The week of April 22 the contractor completed installing water main on the south portion of Valley Lo. The contractor also began standardized testing including pressure testing and chlorinating the new water main in the south portion. The contractor will continue installing new water services to each home in the north area. The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
The week of April 29, 2024 the contractor will continue installing new water services starting where they left off the previous week.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24-25ValleyLo.aspx or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
Phase I Underground work 04/19/2024
The week of April 15 the contractor continued installing water main working towards Wildberry. Throughout this phase of construction, the contractor will be working in the street. installation of the new water main is anticipated to last approximately two weeks.
The week of April 22 the contractor will continue installing water main on the south portion of Valley Lo. The contractor is tentatively scheduled to begin installing new water services to each home..
The new water services connect each house with a new 1.5 copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.
If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.