Valley Lo Water Main Improvements

2024-2025 public improvement project

Road construction
 

The proposed Project includes approximately .7 miles of improvements on Valley Lo Lane from Tanglewood Drive to Wildberry Drive broken down into two phases.

  • Phase I is in 2024 (blue) from Monroe Avenue to Wildberry Drive
  • Phase II is in 2025 (red) from Monroe Avenue to Tanglewood Drive 




The following major improvements are included in this project:


  • ​Installation of approximately 1,600 feet (Phase I) and 1,400 feet (Phase II) of 8-inch Polyvinyl Chloride (PVC) water main with new 1.5-inch water service lines and b-boxes
  • Pavement patching
  • Parkway and driveway restoration for areas affected during construction
  • Resurfacing all of Valley Lo Lane after water main is completed in 2025
Tentative Schedule
  • Bid award date – Anticipated February 2024
  • Resident pre-construction meeting – February 27, 2024​
  • Approximate starting date of construction – March 2024 (Phase I); March 2025 (Phase II)
  • Approximate completion of construction – June 2024 (Phase I); May 2024 (Phase II)

Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.

Capital Improvement Program

The Village annually updates its five-year Capital Improvement Program.


2025 Capital Improvement Program Map


2025-2029 Capital Improvement Program Map


2025-2029 Capital Improvement Program List


2025-2029 CIP Story Map


You can make suggestions and leave feedback about conditions of infrastructure for the next CIP by dropping a pin in this interactive map.

Valley Lo At-A-Glance

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois


Budget: Phase I: $924,000

Phase II: $596,000

Adriana Webb

Engineering Division Manager

(847) 904-4414