The Village of Glenview

Lilac Avenue Improvements


2023 public improvement project

Project Summary

The proposed Project includes approximately 920 feet of improvements on Lilac Avenue from Maple Street to Milwaukee Avenue.

 The following major improvements are included in this project:

 

  • Replacement of 1,136 feet new 8-inch water main with new 1 ½-inch water service lines and b-boxes
  • 1,050 feet of storm sewer improvements
  • Spot replacement of curb and gutter, sidewalk, and driveway apron repairs, as needed.
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

     

    Contractor: Dimeo Brothers, Inc. of Elk Grove Village, Illinois            

    Budget: $1.2 Million​

Project Location Map


Contact Information

Project Manager: Tim Schwister

847-904-4422

tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb

847-904-4414

awebb@glenview.il.us


​​​Tentative Schedule

  • Bid notice published – November 17, 2022
  • Bid opening date – December 6, 2022
  • Bid award – March 21, 2023
  • Pre-construction meeting – May 11, 2023
  • Approximate starting date of construction – July 2023
  • Approximate completion of construction – October 2023

     

    Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.



Notices

Lilac Pre-Construction Meeting Letter.pdf

Handouts

Lilac Design Open House Handout.pdf

Board of Trustees Actions​​​​​

Feb. 7, 2023 -- Lilac-Maclean Contract Award Board Report.pdf


Sign up​ to be emailed project updates.​​