Project Summary​

The Village’s FY204 Road Resurfacing Project includes resurfacing of (19) street sections and one alley (see attached Location Map), as well as the implementation of the annual MARS Program. The MARS program consists of asphalt resurfacing of sections of streets that are less than a complete roadway resurfacing and more than a pothole patching.

The following street sections are planned for asphalt resurfacing in 2024:​​

StreetFrom​To
Fielding DrivePrimrose Lane​Constitution Drive
Constitution DriveFielding Drive ​Independence Ave
Enterprise DriveChestnut Ave​Fielding Drive
Annapolis DriveFielding Drive​Constitution Drive
Nimitz DrivePatriot Blvd​Constitution Drive
Glen Oak DriveNorth End​Ridgewood Lane
Linden LaneWagner Road​West End
Primrose LaneIndigo Lane​Fielding Drive
Flora AveVillage Limits​Fontana Drive
Fontana DriveWashington RoadBel Air Drive
Harrison StreetShermer RoadFlora Ave
Crestwood LaneGlendale RoadEast CDS
Lindenwood LaneGlendale RoadEast CDS
Bellwood LaneGreenwood RoadEast End
Collins AvenueBellwood LaneNorth End
Gregory DriveMilwaukee AveEnd of CDS
Arbor LaneGlenview RoadSouth End
Johns DriveChestnut AveRavine Way
Lincoln Street AlleysGlenview RoadDewes Street
Pfingsten Cul-de-Sac
West EndPfingsten Road


​​Scope of Work

The following major improvements are included in this contract: 

  • Curb and Gutter spot repairs
  • Sidewalk spot repairs
  • Road Resurfacing
  • Parkway Restoration


The Low Bidder information is listed below. 

Contract amount: $2,788,968,000

C
ontact Information

Project Manager: Eric Pugh

847-904-4235

epugh@glenview.il.us​

Senior Project Manager: Thomas Hagerty

847-904-4421

thagerty@glenview.il.us​

Tentative Schedule

  • Bid Notice - February 29, 2024
  • Bid opening date - March 14, 2024
  • Approval of "Resolution for Improvement by Municipality Under the Illinois Highway Code" by the Village President - March 19, 2024
  • Bid award - March 19, 2024
  • IDOT approval of contract - TBD
  • Approximate starting date of construction - May 2024
  • Approximate completion date - August 2024
  • Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.​


Notices