Glenview Road from Milwaukee Avenue to Pfingsten Road and Frontage Road between Nell Lane and Pfingsten Road:

  • Replacement of existing water main
  • Patch asphalt roadway on Glenview Road
  • Resurface asphalt roadway on Frontage Road, including​ spot curb and gutter repairs
  • Restore the parkway

Project information and updates

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,353,333 (bid with River Drive water m​ain replacement project)

Project number: E20-0025

Location map: Click ​here 

Tentative schedule

  • Bid award -- April 8, 2021
  • Resident preconstruction meeting --  April 16, 2021
  • Tentative construction start -- May 3,  2021
  • Tentative completion of construction -- September 30,​ 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.