Meadow Improvements

2025 Capital Improvement Project

Water main
 

The proposed water main project includes approximately 0.4 miles of improvements on Meadow Drive/Lane from Central Road to Greendale Road.

The proposed improvements will consist of:

  • Replacement of the old water main with a new, larger water main
  • Upgrading the water services and b-boxes
  • Sewer repair work as needed
  • Pavement patching
  • Parkway and driveway restoration for areas affected during construction
Tentative Schedule

Bid award date-March 4, 2025

Resident pre-construction- April 8, 2025 @ 6:15 pm

Approximate start date- April 2025

Approximate completion date- Fall 2025

Capital Improvement Program

The Village annually updates its five-year Capital Improvement Program.


2025 Capital Improvement Program Map


2025-2029 Capital Improvement Program Map


2025-2029 Capital Improvement Program List


2025-2029 CIP Story Map


You can make suggestions and leave feedback about conditions of infrastructure for the next CIP by dropping a pin in this interactive map.

At-A-Glance

Contractor: Campanella & Sons

Budget: $1.2 million