Henley Street Improvements

2025 Capital Improvement Project

Water main
 

The proposed project includes approximately 1,100 feet of improvements on Henley Street from Railroad Avenue to Waukegan Road.

The following improvements are included in this project:

  • Replacement of existing water main with new 8-inch diameter water main, including 1 1/2-inch water services and new b-boxes
  • Boring water main under the Metra Railroad
  • Installing additional storm inlets
  • Replacing sanitary structures
  • Roadway reconstruction with new asphalt pavement
  • Install new curb and gutter
  • Driveway replacement (in-kind)
  • Parkway restoration with sod


Tentative Schedule

Contract award- May 6, 2025

Resident Pre-construction meeting- May 13, 2025 @5:30

Anticipated project start- Summer 2025

Anticipated project completion- Fall 2025

Capital Improvement Program

The Village annually updates its five-year Capital Improvement Program.


2026 Capital Improvement Program Map


2026-2030 Capital Improvement Program Map


2026-2030 Road and Infrastructure Program List


2026-2030 CIP Story Map


You can make suggestions and leave feedback about conditions of infrastructure for the next CIP by dropping a pin in this interactive map.

At-A-Glance

Contractor: DiMeo Brothers

Budget: 1.3 Million

Patrick O'Donoghue

847-904-4454