Roosevelt Ave Improvements
2026 Capital Improvement Project
The proposed project includes appproximately 1,900 linear feet of improvements from Swainwood Drive to Glenview Road.
Scope of Work
Reconstruction- Fir St to Prairie St
- Roadway reconstruction with new asphalt, curb & gutter, & replaced sidewalk
- New water main installation with 1.5" services and b-boxes
- Upgraded storm sewer system, including installing new drainage structures
- Sanitary repairs as needed
- Driveway apron replacement (in-kind)
- Parkway restoration with sod
Resurfacing- Swainwood Dr to Fir St
- Roadway resurfacing
- No curb & gutter
- New 5-foot wide concrete sidewalk along the East side of the street to fill in an identified pedestrian gap.
- Driveway apron replacement (in-kind)
- Parkway restoration with sod
Resurfacing- Prairie St to Glenview Rd
- Roadway resurfacing
- New curb & gutter and a slightly narrower roadway to accommodate the new sidewalk
- New 5-foot wide concrete sidewalk along the East side of the street to fill in an identified pedestrian gap.
- Driveway apron replacement (in-kind)
- Parkway restoration with sod
Tentative Schedule
October 28 2025- Design Open House meeting
Nov/Dec 2025- Finalize plans and bidding process
Winter 2026- Contract Award
Feb 2026- Pre-Con Resident Meeing
March 2026- Anticipated Start Date
Late May 2026- Anticipated End Date