Elm St & Hickory Ct Improvements
2026 Capital Improvement Project
The proposed project includes approximately 2.300 LF of improvements along Elm Street and Hickory Court.
Phase I- 2026
- Elm Street- Colfax Ave to McArthur Dr
Phase II- 2027
- Elm Street- McArthur Dr to the South Cul-De-Sac
- Hickory Court- Shermer Rd to Elm St
Scope of Work- Reconstruction Project
- Replacement of existing water main with new 8-inch diameter water main, including new 1.5” water services and new b-boxes.
- Roadway reconstruction with new asphalt pavement, curb and gutter, & sidewalk
- Upgraded storm sewer system, including new drainage structures along the curb & gutter for improved drainage
- Sanitary repairs as needed
- Driveway apron replacement (in-kind)
- Parkway restoration with sod
Tentative Schedule
- Nov 13 2025- Design Open House
- Dec/Jan- Finalize plans and bidding process
- Winter 2026- Contract Award
- Spring 2026- Pre-Con Resident Meeting- Phase I
- Spring 2026- Anticipated Start Date- Phase I
- Spring 2027-Anticipated Start Date- Phase II