Project Summary

The proposed Project includes approximately 690 feet of improvements on Maclean Court from Waukegan Road to the west end of the road.

 The following major improvements are included in this project:

 ​

  • Replacement of 712 feet of new 8-inch water main with new 1 ½-inch water service lines and b-boxes
  • 160 feet of storm sewer improvements
  • Spot replacement of curb and gutter, sidewalk, and driveway apron repairs, as needed.
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

     

    Contractor: Dimeo Brothers, Inc. of Elk Grove Village, Illinois            

    Budget: $778,100​


Project Location Map​


Contact Information

Project Manager: Tim Schwister
(847) 904-4422

tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

​​​Tentative Schedule

  • Bid notice published – November 17, 2022
  • Bid opening date – December 6, 2022
  • Bid award – March 21, 2023
  • Pre-construction meeting – May 11, 2023
  • Approximate starting date of construction – July 2023
  • Approximate completion of construction – October 2023

     

    Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.​


Notices

​​Maclean Pre-Construction Meeting Letter.pdf

Handouts

Maclean Design Open House Handout.pdf

Board of Trustees Actions​​​​​

March 21, 2023 -- Lilac-Maclean Contract Award Board Report.pdf


  
  
  
  
  
  
  
Update
  
  
  
2023 Maclean Court Improvements9/15/2023Published9/8/2023 2:34 PMTim Schwister 847-904-4422On schedule

The week of September 5, the contractor completed the final landscaping including sod.

The week of September 11, the contractor is scheduled to complete the final layer of asphalt. Please watch for handouts letting you know the paving schedule.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023MacleanCourtImprovements.aspx  or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/15/2023Phase III Final Asphalt
  
2023 Maclean Court Improvements9/1/2023Published8/25/2023 3:10 PMTim Schwister 847-904-4422On schedule

The week of August 21st,the contractor completed re-instating the new driveway aprons as well as sidewalks. The contractor will also patch the trenches from the utilities with new asphalt in advance of the pavement milling as well as the final layer of asphalt. The contractor also began installing topsoil in preparation of the new sod tentatively next week.

The week of August 28th, the contractor will tentatively complete the final landscaping including sod. The contractor is tentatively scheduled to complete the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023MacleanCourtImprovements.aspx  or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

 


9/1/2023Final Paving
  
2023 Maclean Court Improvements8/24/2023Published8/18/2023 2:24 PMTim Schwister 847-904-4422On schedule
The week of August 14th, the contractor completed select curb removal and replacement as well as re-instating the new driveway aprons that have been affected by construction.
The week of August 21st, the contractor will complete select pavement patching in advance of the pavement milling. The contractor will also complete select sidewalk remove and replace.
Please watch for further information via the project website at:
https://www.glenview.il.us/Pages/2023MacleanCourtImprovements.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

8/24/2023Phase II Construction